Perth Central Health Campus
Location and Site Area
Perihelion’s first hospital campus – the Perth Central Health Campus (the Campus) - is ideally located at 61 Milldale Way Mirrabooka, 10 km north of Perth’s Central Business District in the City of Stirling.
The site is 12,267 sqm in area.
Demographics
The City of Stirling is located in the northern area of Perth. This area of Perth is the fastest growing area in Western Australia with an 11% growth in 2014. Perth’s northern regions of Stirling and Wanneroo are projected to double to 900,000 residents in the next 15 years (Source: City of Stirling Mirrabooka Area Plan).
Reasons for Selecting this Location
- the geographical centre of Greater Perth;
- 10 kilometres to the Perth Central Business District;
- local council is focussed on high growth and the development of a hospital meets this objective;
- no competitor hospital providing the same services; and
- independent studies show a significant current and growing unmet demand for health services.
Support
Perihelion has gained significant written and / or verbal show of support from:
- Department of Health;
- City of Stirling Council;
- Department of Housing;
- service providers; and
- doctors.
Development Stages
The Perth Central Health Campus will be developed in three distinctive stages which is to be financed by a third party developer at an indicative build cost for Stages One and Two of $188 million. Additional theatre fit out costs for Stage 2 vary between $1 million and $1.5 million each, according to the theatre size. These stages are set out below:
Stage | Build Summary | Facility Summary |
---|---|---|
Stage One - Campus Development Expected completion by December 2018 |
Campus construction 5 stories |
6 theatres 108 inpatient overnight beds 93 day surgery beds Radiology Pharmacy Pathology General practice Consulting suites |
Stage Two – Expansion Forecast start in April 2020; Forecast completion by Sept 2021 |
Fitout of cold shell theatres | 4 additional theatres operationalised (first additional theatre expected to be operational in June 2020) |
Stage Three – Capacity Maximisation Forecast start in January 2026; forecast completion by June 2026 |
Addition of two floors, additional parking. Medi Hotel construction may be included in Stage Three, however, construction timeframe has not been planned. |
Additional facilities: 6 theatres 56 in patient overnight beds 23 day surgery beds Consulting suites |
Who are the Directors of Perihelion?
The Director is Clinical. Assoc. Prof. Rob Will (Managing Director),
Who are the Key Consultants?
The Company currently does not directly employ key consultants, instead, managing a strong team of contractors. This approach has been adopted given the development stage of the business and provides access to world class providers.
The Directors have started a search process for a suitable CEO who will be tasked specifically with the operationalisation and capacity utilisation of the Perth Central Health Campus.
Name of Consultant | Role |
---|---|
Health Projects International Pty Limited | Architects |
Project Directors Australia | Project Managers |
Ralph Beattie Bosworth Pty Limited | Construction Cost Consultants, Quantity Surveyors |